Appendix 3
COSTING DETAILS

CAPITAL COSTS

  1. Site preparation, access: 15 000 LD is allowed for general site clearance, landscaping levelling on the site itself. Costs of landscaping, roads, etc. in the surrounding area are excluded. An additional 5 000 LD is allowed in the second phase to level raceway areas and to create the second roadway.

  2. Office/services building: an initial 300 m2 is allowed, increasing to 500 m2 in phase II. A specialised training building, accomodation, etc., is not included. Estimated price: 180 LD/m2 is allowed; this could be reduced by using modular prefabricated systems.

  3. Hatchery building: an initial 525 m2 is allowed; it is assumed that this will suffice for the second phase. Estimated price for good quality agricultural/industrial warehouse building: 180 LD/m2 ; this could be reduced to 80 LD/m2 for a greenhouse.

  4. Pumps, pump station: a pump well, screen, access, etc., is estimated at 8 000 LD; this is sufficient for both phases. For Phase I, four pumps of 60 kw are assumed at an estimated 7 500 LD/pump, inclusive of local cabling, fittings, central gear. For Phase II a further three pumps would be used. An additional 3 000 LD is allowed for pump bases, installation, etc.; a further 2 000 for phase II.

  5. Water supply and drainage: Phase I: Main pipeline, 2 × 750 mm, 120 m at 50 LD/m including placing, filling; 12 000 distribution bars, allow 1 500 LD, main channel, 35 m at 100 LD/m inclusive; 3 500 LD, raceway channel, 130 m at 60 LD/m inclusive 7 800 LD, other supplies allow 2 000 LD. Drainage 250 m at 20 LD/m allow 5 000 LD. Total 31 800 LD Phase II Add 2 × 750 mm pipeline; 12 000, second raceway channel 7 800 LD, drainage 5 000 LD, Total, including Phase I: 56 600 LD

  6. Hatchery systems: Phase I: Total tank cost 11 500 LD, allow 60% extra for recycle system, 6 900 LD, plus 40 LD/m2 for heating, power, aeration; 21 000 LD Total 39 400 LD

    Phase II. Allow additional 3 000 LD for miscellaneous improvements Total 42 400

  7. Fingerling raceways: Phase I (16) × 15 × 1.5 × 1.2 m deep, reinforced concrete construction, with inlets, outlets, fittings at 25 LD/m3; 10 800 LD. Phase II (32) 21 600 LD

  8. Ongrowing raceways:
    Phase I 45 × 40 × 3.0 × 1.2 m deep at 20 LD/m3 :129 600 LD
    Phase II 95     "       "          "                "273 600 LD

  9. AquacuLture equipment

    Allow 50 LD/t normal production for miscellaneous equipment, plus 5 000 LD (Phase I), 10 000 (Phases I + II) for feeding system

  10. Hatchery and Laboratory equipment: allow 10 000 LD, 15 000 LD respectively

  11. Main services: power supplies; allow 10 000 LD for main supply to site and pumps, 5 000 LD for switch gear, 5 000 LD for site cabling, wiring office/service area. Allow 200 kw generator capacity, phase I, 12 000 LD, double for Phase II, 22 000 LD
    Fresh water supplies: allow 2 000 LD for supply, 2 000 LD for storage and distribution. No extra for Phase II.
    Waste treatment; septic tank, chlorine dosage allow 5 000; drainage piping, allow 3 000 LD. Phone Link: allow 1 000 LD

  12. Vehicles and miscellaneous equipment: Pick-up, cars, etc., allow 12 000 LD, 18 000 LD Phase I, II respectively. Allow additional 8 000 LD for site equipment.

Operations costs details

  1. I Labour: 4 full time staff, plus 2 part-time, allow 4 man/years at 5 000 LD
    II Labour: 6 full-time staff, plus 3 part-time, allow 7.5 man/years at 5 000 LD

  2. Management

    1. 1 Project Manager: 10 000 LD
      1 Hatchery technician and 1 on-growing technician: 2x7 500 LD
    2. 1 more technician

  3. Food

    1. FC: 3:1 150 t at 250 LD/t + 10% transport
    2. Double Phase 1

  4. Power

    1. 108 kw average operating power = 950 000 kwh/year
      allow 204 LD/kwh = 38 000 LD
      Fuel and electricity hatchery: 5 000 LD
    2. Double Phase I

  5. Maintenance

    1. 1% of investment costs
    2. 1% of

  6. Consumables

    1. Artemia cysts: 4 000 LD, stock costs 6 500, others 4 000
    2. Artemia cysts and others: double; stock costs: same phase I (no semi-intensive)

  7. Assume an average 6% of depreciable items; between 4–5% for buildings, tanks, etc., and 25% for vehicles

  8. Based on 12% of fixed capital costs, at 60% mean level

  9. Based on 12% of working capital costs, estimated at 50% of annual operating costs.

Note: Budgets for the national pilot project.

If it is. necessary to allocate capital expenditure to specific project heads, the project may be defined approximately as follows:

 LIB/86/002LIB/86/008Other
Main site works, clearance--X
Pump station, one pump pipe, main channelX--
Other water distribution--X
Fingerling racewaysX--
Hatchery buildingX--
Hatchery systemX--
Hatchery/Lab equipment-X-
Office/services buildingX--
Equipment-X-
Aquaculture equipment-X-
Main raceways--X
Power, freshwater, phone, etc.--X